Stansbury Park Observatory Complex 3 (SPOC 3)
200 mm Refractor Observatory
Inception Through Getting the Floor Ready to Pour
(click on images to see a larger picture)
Back to Observatories
Page
001 - 12 OCT 2002

Ron Ford took this photo of SPOC from above. Current plans
have the refractor observatory being built to the left of the Harmons
observatory where the old SPOC dome currently sits.
002- 30 NOV 2003

Bruce Grim built this model showing how the
observatory will look. Note that the old SPOC dome will be used in keeping with
the wishes of the surrounding community. However, it will not rotate and the
shutter will be welded shut. As the model shows, to expose the telescope to the
sky the dome will roll off to the north. When closed the inside of the dome
will double as a projection screen for a simple planetarium star projector so
the public can be shown during daylight what they'll be seeing that night.
003 - 30 NOV 2003

An early and preliminary drawing showing a front view
of the observatory (PDF file).
004 - 30 NOV 2003

An early and preliminary drawing showing a top view of the
observatory (PDF file).
005 - 30 NOV 2003

Kim Hyatt, Patrick Wiggins, Ken Harris, Boyd McNeil Andy
Bogdan and Bruce Grim meet to discuss the new building.
006 - 30 NOV 2003

Project architect Kim Hyatt (Left) explains a preliminary set
of drawings.
007 - 09 DEC 2003

Bruce Grim, Patrick Wiggins and Roger Butz struggle to load
the refractor mount onto the truck.
008 - 09 DEC 2003

Bruce Grim and Roger Butz use a winch to unload the refractor
mount.
009 - 09 DEC 2003

Bruce Grim with the refractor mount. Once he does a little
cosmetic work on the mount it will be moved to SPOC.
010

SLAS Sec/Treas Charlie Green receives a $12,500 check for the Refractor House from SLAS member Siegfried Jachmann as SLAS president Ken Harris looks on. The check was a donation from Leucadia Corporation. 23 MAR 2004
011 to 015
Planting the light shield hedge (aka biophoton shield) around the SPOC perimeter and weeding the existing hedge. Wayne Clarke and Daniel Turner also helped but managed to avoid getting their pictures taken. 17 APR 2004
011

Boyd McNeil
012

Patrick Wiggins
012

Roger Butz & Ken Harris
013

Ann House, Ken Harris & Boyd McNeil
014

A bit of weeding
015

Bruce Grim & Quintin Foster
016 to 019
SPOC committee members meet with Roen Hale who agreed to help locate the steel that will be needed for the Refractor House at a good price. 21 APR 2004
016

Andy Bogdan, Ken Harris, Bruce Grim and Roen Hale
017

Roen Hale, Siegfried Jachmann and Kim Hyatt
018

Roen Hale & Siegfried Jachmann
019

Siegfried Jachmann & Patrick Wiggins
020 & 021
Donation presentation at the 27 April 2004 SLAS general meeting.
020

SPOC Committee Chairman Siegfried Jachmann "accepts" a donation check for $7,500 from Patrick Wiggins for the Refractor House as SLAS president Ken Harris looks on.
021

Patrick Wiggins presents a donation check for $7,500 for the Refractor House to SPOC Committee Chairman Siegfried Jachmann as SLAS president Ken Harris looks on.
Moving the dome aside in preparation for start of construction. 05 MAY 2004
022

Roger Butz, Boyd McNeil and Ron Ford help with emptying the dome (it had been used as a storage facility for nearly 2 years).
023

Ron Ford, Dave Bennett, Andy Bogdan, Ken Harris, Bruce Grim and Roger Butz finding out a _lot_ had been stored in the dome.
024

Kim Hyatt & Dave Bennett salvage usable parts from the structure that once held the very first SPOC telescope.
025

Dave Bennett jacks up one side of the dome.
026

Andy Bogdan, Patrick Wiggins and Wayne Clarke jack up the other side of the done. Ron Ford image.
027

It was found that more mass was needed on the lever. Ron Ford image.
028

Placing the rails. Ron Ford image.
029

030

Initial placement of the rails. Eventually used only one rail in the center. Ron Ford image.
031

Ropes and cables being attached to Bruce Grim's truck as Dave Bailey and Quinten Foster check to see the ropes are positioned properly on the back side of the done..
032

Ropes and cables attached. Ron Ford image.
033

The dome starts to move. Note the rails that had been installed for the dome to slide on.
034

A section of rail being moved from the rear to the front.
035

Call the astrologers! Crop circle sighted at Stansbury Park!
036

Dome in it's final location (for now) and being refilled.
037

The footers were dug today. 18 JUN 2004
038

This picture was taken to answer the oft asked question, "How deep was the hole for the pier?" Boyd McNeil image 18 JUN 2004
039

Boyd McNeil photodocuments the first day of work on the Refractor House. 18 JUN 2004
040

Mark Olsen, owner of I D Electric, installs electrical conduit as Bruce Grim looks on. 23 JUN 2004
041

Patrick Wiggins stands next to the conduit that will carry electrical power to the refractor pier. 23 JUN 2004
042

Bruce Grim checks the rebar. 23 JUN 2004
043

Site awaits arrival of the cement trucks. 23 JUN 2004
044

The pouring has started under the direction of Gordon Fields, owner of Fields Quality Concrete & General Construction. 24 JUN 2004
045

Vibration isolation pads are placed around the telescope pier's base by Gordon Fields. 24 JUN 2004
046
|
047
|

|

|
Gordon Fields smoothes out the surface. 24 JUN 2004
048

Foundation and floor are finished. 24 JUN 2004
049

The traditional inscription. This one is located between where the telescope bay's two doors will be. 24 JUN 2004
|