Ground heaving cracked a number of the slab sections necessitating their removal and reinstallation.

001

Before the slab sections could be cut Bruce Grim, Roger Butz, Andy Bogdan and Patrick Wiggins remove the snow and ice.  22 FEB 2002  Ron Ford image

002-007
******

******
Ron Ford, Andy Bogdan, Bruce Grim, Patrick Wiggins Boyd McNeil and Roger Butz take their turns running the concrete cutting saw. 22 FEB 2002

008

Roger Butz and Ron Ford try a bit of "curling on concrete".  22 FEB 2002

009

Roger Butz takes advantage of Patrick Wiggins being a vegetarian.  22 FEB 2002  Ron Ford image

010

With the cuts finished Andy Bogdan and Roger Butz use pry bars to lift a section of concrete.  22 FEB 2002

011

Stansbury Park Service Agency's Colton Park uses the back hoe to remove the buckled pieces of concrete.  25 FEB 2002  Ron Ford image

012

After the concrete was removed.  26 FEB 2002

013

Roger Butz digging the north drainage trench.  26 FEB 2002  Ron Ford image

014

The west drainage trench.  28 FEB 2002

015

The north drainage trench.  28 FEB 2002

016

The east drainage trench.  28 FEB 2002

017

Sump at the south end of the east drainage trench.  28 FEB 2002

018

Ron Ford adds gravel to the east drainage trench.  01 MAR 2002

019

Bruce Grim struggles with a section of perforated drain pipe.  01 MAR 2002

020

Bruce Grim and Ron Ford pull filter cloth over a section of perforated drain pipe.  The cloth allows water to pass into the pipe but keeps mud & rocks from plugging the pipe's perforations.  01 MAR 2002

021

Patrick Wiggins levels the gravel in the bottom of the west drainage trench.  01 MAR 2002  Ron Ford image

022

Drain pipe in the west drainage trench and ready to be covered.  01 MAR 2002

023

Drain pipe and a top layer of gravel has been installed in the north drainage trench.  01 MAR 2002  Ron Ford image

024

Drain pipe and a top layer of gravel has been installed in the east drainage trench.  01 MAR 2002  Ron Ford image

025

Stansbury Park Service Agency's Colton Park uses the back hoe to fill in the drainage trenches. 06 MAR 2002

026

Trenches filled and area ready for landscaping.  06 MAR 2002