SLAS's own Ken "Red Baron" Warner took this photo of SPOC in October
2000. Note that the new observatory will be built to the left of the current
dome near the lower soccer field goal post (the soccer field will be moved
to the east).
002
Model of the Harmons Observatory at SPOC 2 as viewed from the southeast.
Only one of the two slide off roofs is shown. The 40 cm (16") Ealing
scope is shown in the foreground while an early (now abandoned) design
of the 81 cm (32") scope is shown in the rear. The center room will
serve as a control & storage room (its roof will not move).
003
Model of the Harmons Observatory at SPOC 2 as viewed from the northwest.
004
Model of the Harmons Observatory at SPOC 2 as viewed from the southwest.
005
Roger Butz, Patrick Wiggins and Bruce Grim during an early survey
of the site, Fall 1999. McNeil photo
Images 005 & 006: SPOC 2 Committee Meeting, 18 NOV 2000.
McNeil photos
006
Committee members meet for "Advanced Training" at the Flying J
to discuss progress and plans. 007
Bruce Grim's arm is bitten as he puts a hex on Patrick Wiggins
(Actually it's Bruce pointing out features at the SPOC 2 site).
008
Ken Harris, Boyd McNeil & Andy Bogdan survey the site, 21 FEB
2001. McNeil photo 009
Andy Bogdan drives a survey stake as Ken Harris and Bruce Grim
look on, 21 FEB 2001. McNeil photo "Real" ground breaking for SPOC 2 010
Back hoe and operator (provided at no cost to SLAS by Stansbury
Park) making the
first "real" dig at SPOC 2 on 01 MAR 2001. McNeil photo
011
Roger Butz, Bruce Grim and back hoe driver Colten Parks inspect
the site shortly after Colten removed the sod, 01 MAR 2001. McNeil photo
012
Roger Butz, Bruce Grim and Andy Bogdan survey the site, 01 MAR
2001. McNeil photo 013
Bruce Grim, Andy Bogdan and Roger Butz prepare the site, 01 MAR
2001. McNeil photo "Official" ground breaking for SPOC 2 014
SLAS President Siegfried Jachmann addresses the crowd prior to
the official SPOC 2 groundbreaking, 03 MAR 2001. McNeil photo
015
Several members head to the official SPOC 2 groundbreaking, 03
MAR 2001. McNeil photo 016
Siegfried Jachmann, Bruce Grim, Mark Meadows, Vaughan Parsons,
Patrick Wiggins and Bill Richardson prepare to dig in at the SPOC 2 ground
breaking ceremony on 03 MAR 2001. Photo by Rich Tenney
017
Siegfried Jachmann, Bruce Grim, Mark Meadows, Vaughan Parsons,
Patrick Wiggins and Bill Richardson with "first dirt" at the SPOC 2 ground
breaking ceremony on 03 MAR 2001. Photo by Rich Tenney
018
SPOC 2 engineer Reinhardt Bsumek speaks with SLAS President Siegfried
Jachmann after the official groundbreaking, 03 MAR 2001. McNeil photo
019
Devra Filler and her daughter Katie enjoy the official groundbreaking,
03 MAR 2001. McNeil photo
020
Several members celebrate the official groundbreaking, 03 MAR 2001.
McNeil photo
021
Pier holes ready for concrete, 13 MAR 2001. McNeil photo
022
Roy Lacy, Bruce Grim, Andy Bogdan and Roger Butz prepare the pier
holes for filling, 13 MAR 2001. McNeil photo
023
Roy Lacy, Bruce Grim and Roger Butz prepare the pier holes for
filling, 13 MAR 2001. McNeil photo
024
Roy Lacy appears to be sleeping on the job but is actually eyeballing
the pier hole forms, 13 MAR 2001. McNeil photo
025
Roger Butz and Andy Bogdan level the pier forms, 16 MAR 2001.
McNeil photo
026
Roy Lacy and Roger Butz eyeballing the forms, 16 MAR 2001.
McNeil photo
027
Roy Lacy, Roger Butz, Bruce Grim and Andy Bogdan adjusting the
pier forms, 16 MAR 2001. McNeil photo
028
Bruce Grim drilling holes for conduit, 16 MAR 2001. McNeil
photo
029
Boyd McNeil spraying the Ealing pier forms while Bruce Grim and
Andy Bogdan work on the "Big Scope" pier forms, 16 MAR 2001. McNeil
photo
030
Bruce Grim, Roger Butz and Andy Bogdan during the first pier pour,
16 MAR 2001. McNeil photo
031
Andy Bogdan, Bruce Grim and Roger Butz finishing the piers, 16
MAR 2001. McNeil photo
032
Newly poured cement piers covered with tarps. The pier for
the 81 cm (32") telescope is in the foreground, 17 MAR 2001.
033
Bruce Grim with the Simpson Steel truck used to deliver the concrete
reinforcing bar, 16 MAR 2001. McNeil photo
034
Colten Parks unloading rebar, 16 MAR 2001. McNeil photo
035
Bruce Grim demonstrates the depth of the foundation (actually he
was kneeling), 21 MAR 2001. McNeil photo
036
Andy Bogdan prepares floor forms, 21 MAR 2001. McNeil photo
037
Roger Butz, Bruce Grim, Andy Bogdan and Ken Harris prepare floor
forms, 21 MAR 2001. McNeil photo
038
Boyd McNeil dumps a load of gravel, 21 MAR 2001. McNeil photo
039
East end of the building showing the Ealing pier base. Black
pipe will be buried in the concrete and be used to run control and imaging
cables between the Ealing and the control room, 22 MAR 2001.
040
West end of the building showing the pier base for the 81 cm (32")
telescope, 22 MAR 2001.
041
Building site, looking to the east, 22 MAR 2001.
042
Bruce Grim cutting conduit, 22 MAR 2001. McNeil photo
043
Bruce Grim tying rebar for the floor, 22 MAR 2001.
044
Andy Bogdan & Wayne Clarke confer with Bruce Grim as Boyd McNeil
looks on, 23 MAR 2001.
045
Bruce Grim, Siegfried Jachmann and Mr. Milan (with CPC Concrete),
22 MAR 2001. McNeil photo
046
Robert St. Marie tying rebar, 22 MAR 2001. McNeil photo
047
Wayne Clarke working with rebar, 22 MAR 2001. McNeil photo
048
Patrick Wiggins tying rebar for the floor, 23 MAR 2001.
049
"First blood". Patrick Wiggins shows the effects of flying
rebar on a hard head, 23 MAR 2001.
050
Much work going on as President Jachmann mans the desk, 23 MAR
2001.
051
Siegfried Jachmann making sure Bruce Grim gets it right, 23 MAR
2001. 052
Rebar work nearly complete, 23 MAR 2001.
053
Siegfried Jachmann inspecting the nearly completed floor rebar
work, 23 MAR 2001.
054
Bruce Grim & Siegfried Jachmann schmoozing the building inspector,
23 MAR 2001.
|