001
Steel for the roof beam, dome trolley and trolley tracks, donated
by Roen Hale and Jerry Clegg, has been delivered. 22 JUL 2005
002
Patrick Wiggins chisels away the shutter's deteriorated side
pieces.
29 JUL 2005
003
Bruce Grim watches as Colter Park attaches lifting chains to a
section of dome track support. 02 AUG 2005 Boyd McNeil
image.
004
The east dome track support is set in place. 02 AUG
2005
Boyd McNeil image.
005
Colter Park approaches with the west dome track support.
02 AUG 2005 Boyd McNeil image.
006
Andy Bogdan and Ken Harris ensure the west dome track support is
placed properly. 02 AUG 2005 Boyd McNeil image.
007
Both dome track supports tacked in place, awaiting the
welder.
02 AUG 2005
008
Both dome tracks tacked in place, awaiting the welder. 03
AUG 2005
009
Close-up showing how the grooved dome trolley wheels will fit on
the tracks. 03 AUG 2005
010
Patrick Wiggins and Bill Kennedy work to remove the shutter motor
mount bolts. 14 AUG 2005 Boyd McNeil image.
011
Guy Malmborg removes the shutter motor. 14 AUG 2005
Boyd McNeil image.
012
Shutter motor removed. 14 AUG 2005
013
Lower shutter removed and laying on the ground, upper shutter is
next. 14 AUG 2005
014
Bill Kennedy looks on as Guy Malmborg gets ready to pull down the
upper shutter (and to run!). 14 AUG 2005
015
Bill Kennedy, Patrick Wiggins and Guy Malmborg prepare to position
the new lower shutter. 14 AUG 2005 Boyd McNeil image.
016
SLAS photographer Boyd McNeil covers the action. 14 AUG 2005
017
Patrick Wiggins grinds off an old weld. 14 AUG 2005
Boyd McNeil image.
018
Guy Malmborg welds a new support in place. 14 AUG 2005
019
Guy Malmborg shows how to operate two grinders at once (must be
his Marine training). 14 AUG 2005 Boyd McNeil image.
020
Bill Kennedy and Guy Malmborg install an internal support.
14 AUG 2005
021
Bill Kennedy and Guy Malmborg position the new lower shutter.
14 AUG 2005
022
Guy Malmborg welds the lower shutter in place. 14 AUG 2005
023
Patrick Wiggins prepares the track for the upper shutter.
14 AUG 2005
024
Guy Malmborg administers the Imperio as Patrick Wiggins welds the
upper shutter in place. 14 AUG 2005
025
Guy Malmborg admires the results of several hours work. 14
AUG 2005
026
That's not the final color. Bruce Grim applied a coat of
red primer today which will eventually be covered with white. 15
AUG 2005
027
Ken Harris and Bruce Grim check to be sure the dome trolley is
laid out correctly as the hired certified welder welds the pieces
together.
17 AUG 2005
028
Ken Harris, Andy Bogdan and Bruce Grim adjust a corner of the dome
trolley. 17 AUG 2005
029
Bruce Grim, Andy Bogdan and Ken Harris discuss putting up the
storage
room roof. 17 AUG 2005
030
Ken Harris works on the storage room roof. 17 AUG 2005
031
Patrick Wiggins works on the storage room roof. 17 AUG 2005
032
Patrick Wiggins and Ken Harris install one of the storage room
rafters. 17 AUG 2005 Boyd McNeil image.
033
Storage room roof rafters in place. 17 AUG 2005
034
Andy Bogdan, Patrick Wiggins and Ken Harris fasten the storage
room rafters in place. 14 AUG 2005 Boyd McNeil image.
035
SPOC superintendent Bruce Grim "superintending". 18 AUG
2005
Boyd McNeil image.
036
Bruce Grim applies a coat of red primer to the I beam that will
support the dome's crane and star projector. 18 AUG 2005
037
Andy Bogdan and Ken Harris pass a piece of roofing up to Patrick
Wiggins. 18 AUG 2005
038
Bruce Grim caulks storage room roofing joints. 18 AUG 2005
039
Storage room roof ready for painting. 18 AUG 2005
040
Storage room roof painted, awaiting waterproof membrane.
18 AUG 2005
041
Storage room from below. 18 AUG 2005
042
Patrick Wiggins jacks up the dome. 19 AUG 2005
043
Dome off the ground and up on blocks. 19 AUG 2005
044
Patrick Wiggins works to remove the no longer needed dome rotation
cable channel. 20 AUG 2005
045
Patrick Wiggins cuts out one of the dome shutter side panels.
20 AUG 2005
046
Quintin Foster observes as Ken Harris cuts a piece of storage room
roof membrane. 30 AUG 2005 Boyd McNeil image.
047
Quintin Foster and Andy Bogdan apply adhesive as Ken Harris, Bruce
Grim and Patrick Wiggins watch. 30 AUG 2005 Boyd McNeil
image.
048
Quintin Foster, Ken Harris, Patrick Wiggins and Andy Bogdan roll
a piece of storage room roof membrane into place. 30 AUG
2005
Boyd McNeil image.
049
Storage room roof membrane in place. 30 AUG 2005
050
Dome trolley "up on blocks" with crane/star projector I beam in
place. 31 AUG 2005